Upgrades To Power Supplies
Posted by Karl @ Macintosh Electronics Ltd Help Desk on 15 October 2014 12:06 pm |
|
Upgrades to power supplies at 20 BT exchanges
Contractors will be replacing the UPS and Auto Transfer Switches to the following schedule
Mon 20/10/2014 Nottingham Tue 21/10/2014 Sheffield Wed 22/10/2014 Leeds Thu 23/10/2014 Newcastle Fri 24/10/2014 Peterborough Mon 27/10/2014 Manchester Tue 28/10/2014 Preston Wed 29/10/2014 Edinburgh Thu 30/10/2014 Glasgow 3/11/2014 Bristol 4/11/2014 Cardiff 5/11/2014 Birmingham 6/11/2014 Wolverhampton 7/11/2014 Milton Keynes Mon 10/11/2014 Slough Tue 11//11/2014 Stepney Green Wed 12/11/2014 Colindale Thu 13/11/2014 Columbo Fri 14/11/2014 Kingston Mon 17/11/2014 Faraday The work is planned from 08:00 - 18:00 each day. No downtime is expected, there is a small risk of power loss if the building power fails while the UPS are changed. | |